One play from the tronghieu/agent-skills scrum-master set (MIT), imported on its own (owner-approved acquisition, gap report row 18). The set's init script and its other plays are NOT imported. Fleet note: this fleet's sprints close on scope completion, not on a calendar; read any fixed-cadence wording accordingly — it has been stripped where the source carried it.

close-sprint — the Mirror play​

Run on the last day, after the review.

  1. Final fetch or export — same source rules.
  2. Fill the close snapshot:
## Close snapshot — written 2026-09-04, immutable

| Metric | Value | Source |
|--------|-------|--------|
| Committed | 34 pts / 8 stories | planning section above |
| Added mid-sprint | 8 pts / 3 stories | SC-1..SC-3 |
| Delivered | 21 pts / 5 stories | Jira export 2026-09-04 |
| Carry-over | 13 pts / 3 stories | Jira export 2026-09-04 |
| Velocity | 21 pts | delivered points |
| Goal | partial — onboarding behind flag, not GA | review demo 2026-09-04 |
| Impediments | 2 opened, 1 closed; IM-2 open 11d | impediments.md |
  1. Set status closed. The snapshot is never edited afterward — a later correction is a dated addendum line beneath it, with the original left standing. Snapshots are the team's memory; memory you can rewrite is not memory.
  2. Offer the retro; the snapshot is its data pack's first row.

Source: tronghieu/agent-skills · @ 1a4b81dc6964 · skills/scrum-master/references/sprint-loop.md (close-sprint section) · Imported 2026-10-07, acquire-adapted. License MIT.